Charlesview inspection reports now online

Read for yourself about the management situation at Charlesview. Charlesview knows in advance when these inspections will be done. Why didn't they correct these many easily correctable violations before the inspectors arrived?

The BRA was right in their Scoping Determination to require that:

"Assurances must be clear, exact and extensively detailed in the DPIR as to how the Proposed Project, if approved, will be maintained to avoid and minimize future neglect"

But the DPIR provides no such information. Why has the BRA backed down from this requirement?

http://www.scribd.com/doc/22491496/Charlesview-HUD-Inspections

Pagliuca's Allston plan and Harvard's Allston attitude

If our federal and state tax dollars are going to directly fund construction of Harvard's Science Complex, then I think it would be appropriate to see some changes to the design and attitude driving that project.

During the review process I noted that Harvard made bogus claims about public spaces in the buildings and the general attitude that the four-building complex was for Harvard and Harvard people, not for Allston/Brighton and its residents. So Harvard told us to keep out of the Science Complex's fitness center ("sorry, too small"), keep out of the private rooftop restaurant and bar ("sorry, security threat"), keep out of the Harvard shuttle buses (a security or insurance risk) and keep our kids out of the daycare (unless your kid is one of the 15%). Harvard designed a first floor with little retail or restaurants and eliminated the small museum-type space that was in the initial plan.

Overall, Harvard chose to ignore the many opportunities to have the complex help make Western Ave more vibrant, remove town/gown barriers, and think about how this massive complex and first step in the campus expansion could also be a first step in a neighborhood renaissance.

While I still disagree with Harvard's approach, if they were building the entire complex with private funds I guess you could say "it is their money so they can do what they want with it." Well, if instead it is going to be partially funded with our money then a very different attitude would be appropriate.

Stephen Pagliuca has Allston plan - BostonHerald.com

Video of Harvard & Allston on WGBH's Greater Boston

Thanks to Emily Rooney and the Greater Boston team for this great show!





Harvard & Allston tonight on Greater Boston

Tonight on Greater Boston with Emily Rooney
Tuesday, November 10, 7pm and 12midnight
WGBH 2/HD
Repeats weekdays 5am, 11am, 11pm, WGBH World
Sundays 9:30am, WGBH 44
Or watch it On Demand on Comcast 1

Harvard's Allston Expansion

Citing the recession and it's major impact on the university's endowment, Harvard continues to re-assess it's expansion plan in Allston. A number of Allston residents are upset over stalled construction and vacant buildings in the neighborhood. Tonight Emily is joined by Brent Whelan of the Allston-Brighton North Neighbor's Forum, Kevin McCluskey of Harvard University and Michael Glavin, the deputy director of the Boston Redevelopment Authority.

Charlesview at Boston Civic Design Commission meeting tonight

Please join neighbors from Allston and Brighton to ask the Boston Civic Design Commissioners to withhold approval of the Charlesview project until the major design flaws with this proposal are resolved.

Especially if you work downtown, in Kendall Sq, or anywhere else where you aren't too far from City Hall, it would be a great help if you can spend 1/2 hour to show that we care about the future of our neighborhood and want to improve the current proposal instead of settling for this second-rate design.

5:20 - 5:40 Report from Design Committee: Charlesview Relocation Project
Piemonte Room, 5th floor, Boston City Hall

Here is one example of how the current proposal could be much better. Here are 7 proposed buildings each with a thin strip (probably 5-10 feet) of grass on the sides. The block contains 24 units (18 condos and 6 apartments). Instead of backyards for these 24 units, the space behind the buildings is a 14 car parking lot.

Maybe some people would be OK with a parking lot instead of a backyard, but this sure would be nicer if the parking could be added to the proposed 260-car underground garage or done with a combination of driveways, garages, and on-street parking.

Would the real Charlesview please stand up?

Each HUD inspection report summarizes the "systemic deficiencies" found during the inspection. From what has been said in various forums, one might think that Charlesview needs extensive and expensive repairs. For example, in the DPIR, Charlesview states:

"Now nearly 40 years old, the existing Charlesview property has reached the end of its useful life and requires redevelopment to continue its legacy as a critical housing source for North Allston Brighton."
But the HUD reports tell a very different story - it is almost as if there are two different Charlesviews:

- There is the Charlesview that we hear about from Charlesview's Board, The Community Builders, the BRA, and our elected officials. This Charlesview is about to crumble to the ground and must be evacuated ASAP.

- There is the Charlesview that is inspected every couple years by HUD with a long list of "ordinary" problems but in need of almost no major repairs.

As the host used to ask on To Tell The Truth...

"Would the real Charlesview please stand up?"

The reports categorize systemic deficiencies in two ways:

  • Capital items that generally require large cash outlays (such as new roofs and new appliances)

  • Ordinary items are repairs that require smaller cash outlays (such as light fixtures, fire extinguishers, and smoke detectors)
Date Capital Items Ordinary Items
March 2002
Bathroom sinks damaged or missing
Obstructed or missing accessibility routes
Broken/missing/cracked window panes
Auxiliary lighting inoperable
Damaged door hardware/locks
January 2004 Bathroom sinks damaged or missing
Auxiliary lighting inoperable
Damaged door frames
Electrical covers missing
Damaged door surfaces
Damaged door hardware/locks
March 2005 none none
April 2008 none 16 unique defect types
August 2008 none

Obstructed or missing accessibility routes
Walls stained/peeling/needs paint
Lighting missing/damaged
Damaged door surfaces
Damaged door hardware/locks


So according to HUD's inspectors, Charlesview for the past 4 years hasn't needed any major capital improvements and in the past 7 years the only capital repair needed was new sinks in some bathrooms. At the same time, there are many smaller things not being done to HUD's standards including fences that need to be repaired, grass that needs to be mowed, light switches that need covers, fire exits that are blocked, walls that need to painted, etc.

This does not support the claims that Charlesview has been fundamentally flawed since its construction or that the buildings are in urgent need of replacement. These reports do indicate that basic, regular maintenance at Charlesview has been highly inconsistent during the past several years.

Thank you for helping the Zepeda family

Thanks to the many residents of Allston and Brighton who contributed to the family of the late Fredy Zepeda. Earlier this year, Mr. Zepeda was struck and killed by a car in Brighton. His wife and child needed help and financial contributions from our community have helped them to pay their daily life expenses.

Man killed in Allston this morning

Stabbing death in front of the Store24 at 157 Brighton Ave (at the intersection with Harvard Ave) early on Sunday morning.

BPDNews.com - News Updates from the Boston Police Department

HUD releases Charlesview inspection reports

We have heard a lot of vague statements over the years about the condition of the Charlesview Apartments. Now, thanks to HUD and a FOIA request, we have public information from the past several years from independent, certified inspectors. The format and definitions of the reports are described at http://www.disasterhousing.gov/offices/reac/products/pass/pass_isrpt.cfm.

When I am near a scanner I will upload the full reports, but in the meantime, here are the number of Health and Safety deductions made during each report (higher numbers indicate more problems).
March 2002 4.1
January 2004 17.0
March 2005 6.0
April 2008 24.2
August 2008 7.3

The April 2008 report gave Charlesview an overall score of 50 out of 100, and HUD wrote that "the inspection has been referred to the Departmental Enforcement Center for enforcement action... Properties scoring below 60 have physical deficiencies that do not meet the contractual obligations to HUD. Residents of such properties are not receiving the quality of housing to which they are entitled."

However, four months later Charlesview had been able to correct almost all of these problems. This contradicts the oft-repeated statements that the condition of Charlesview is so intolerable and the problems there are too difficult to fix.

Enrichment Showcase at the Gardner

One of the many great programs at the Gardner Pilot Academy in Allston is the Friday Enrichment program. This program brings a wide range of artists and other adults from the community into the school on Friday mornings to do creative, fun, and educational activities with the kids. This morning was one of the "showcases" that the school has a few times a year when the students perform and show their work to their classmates and families.



Do PILOT & Allston/Brighton negotiations conflict?

This story doesn't mention Harvard, but obviously if the Mayor and City Council are negotiating with Harvard and other non-profits about PILOT payments, I wonder how this impacts the negotiating that many of us think the Mayor and City Council should be doing with Harvard to allow more land in the Holton St Corridor to be developed for Charlesview and other developments.

More PILOT money is of course good for the entire City, while ending Harvard's landbanking would be good for Allston and Brighton. So when the Mayor's people and Harvard's people are discussing these issues, which one comes first?

Murphy says PILOT deal is on its way Jamaica Plain Gazette
"But the government and institutions are negotiating well now, Murphy said, describing positive progress. Because the city cannot legally require any PILOT deals, the agreement will rely on goodwill and political pressure. "

Smith Asks BRA For Some Respect

Allston resident Karen Smith has a Letter to the Editor in today's Boston Herald

Allston dissed - BostonHerald.com

Upcoming zoning hearing

60 North Crescent Circuit - Remove and rebuild existing rear porch

http://www.cityofboston.gov/ons/pdfs/allstonbright.pdf

Rats Rats Rats

The Phoenix takes an in-depth look at the Boston rat rampage in Allston and across the City.

DiCara hits Harvard for landbanking

Nice to see another voice in support of active uses for what is now mothballed.

The Harvard Crimson :: News :: Menino Elected for Fifth Term
Former City Councilor mayoral candidate Lawrence S. DiCara ’71, who said he continues to follow Boston politics closely, described the mayor’s relationship with Harvard as “cooperative.” “They’ve been working together on Allston,” DiCara said. “That doesn’t mean that Harvard can buy up land and do nothing with it, though.”

ABNNF meets Thursday

All are welcome to join the ABNNF at 6:00 on Thursday to discuss the Charlesview relocation and Holton Street Corridor redevelopment. City Councilor Mark Ciommo will join us for this meeting which will be held in the Gardner School auditorium (30 Athol St).

Precinct by Precinct results from Nov 3

For anyone interested in the finer details of yesterday's results
http://www.scribd.com/doc/22110930/Boston-Election-Results-November-3-2009

Map of wards and precincts
http://www.cityofboston.gov/maps/pdfs/ward_and_precincts.pdf (small file)
http://www.cityofboston.gov/maps/pdfs/ward_and_precinct_withstreets.pdf (larger file)

Election results rolling in

The race for Mayor is still within a few percentage points, but it seems clear that Mark Ciommo is heading to a victory in his City Council race vs. Alex Selvig.

Congratulations to Mark and thank you to Alex for his willingness to challenge an incumbent - an uphill battle in any election but one that also strengthens our democracy and civic life.

http://www.cityofboston.gov/elections/currentelections/

Voted yet?

Polls close at 8pm

Leadership Without a Secret Code

It is a surprising title for this interview, considering the intense secrecy with which Harvard's guards its plans here in Allston and "communicate, communicate, communicate” is certainly not the mantra of the Allston Development Group.

The morsel that seems most consistent with Harvard's situation in Allston is this idea that Faust got from HBS Prof Michael Porter - “Strategy is what you choose not to do.”

Corner Office - Drew Gilpin Faust - Leadership Without a Secret Code - NYTimes.com